Week Nr: 81
   
Week Commencing: 21st April 2014
   
Description of Works:

Ysgol Y Deri

The multi purpose/ main hall ceiling is now being decorated and we will be taking the scaffold to this area down next week.

High level lighting has been installed into the sports hall/ trampoline room, Which now completes the majority of the ceiling works, enabling us to concentrate on the preparation for the trampoline installation.

Data cabinets are being installed to electrical cupboards.

Doors and furniture are now 80% complete.

Fixed furniture is now 80% complete with ceramic tiles and plumbing being completed after installation.

Mechanical and electrical installation is now at final fix stage.

Flooring is now 75% fitted in all the classrooms.

St. Cyres School

This week the lab furniture in the science department has progressed with some labs being completed along with the vinyl flooring

The Main hall has had its ceiling completed, decoration is well underway and some light fittings have been installed prior to the flooring being started next week.

The sport equipment has been installed in the sports hall and the external doors fitted, the ceilings in the changing rooms have been constructed and are awaiting plasterboard.

The Maths and English departments have been fully decorated along with the Languages department.

The vinyl flooring to the CDT and Art departments is finished and the decoration is coming to completion.

The SEN department has been decorated and is ready to be snagged.

Respite Centre

Suspended ceiling grid progressing well both floors.

IPS frame work / panelling to the wet areas and W/C are progressing well.

Installations of the door linings/ frames ongoing to both floors.

Skirting and architrave ongoing to first floor.

External render ongoing.

Decoration ongoing to both floors.

Stair balustrade ongoing.

External timber cladding ongoing.

   
Site Phasing Plan: PLC Building Phasing Plan
   
Community Engagement:

We are very pleased to have received confirmation of the Penarth Learning Community project being short listed for 2 Constructing Excellence Wales awards.

We have been short listed for the following:

- Sustainability Award
- Innovation Award.

We will be delivering presentations to the judges during May and will then find out if we’ve won during an award ceremony on 4th July.

Until then, our fingers are crossed!