Week Nr: 82
   
Week Commencing: 28th April 2014
   
Description of Works:

Ysgol Y Deri

The scaffold has been stripped and the first coat of Decoration to the Multi purpose hall has been applied

The scaffold to the trampoline pit has been stripped and a temporary safety hand rail has been fitted, this will enable works within the pit to begin.

Ceramic tiling to all WC and hygiene areas is 90% complete.

The Resin flooring to the 1st level is now 100% complete, with the floor coverings to the rest of the communal area s to follow.

Doors and handles now 90% complete.

Mechanical and electrical installation/final fix is still ongoing.

St. Cyres School

The 6th form area was locked down ready for final Desnag and the corridor ceiling in this area was prepared for decoration.

The Science department’s fixed furniture was completed and protected to allow decoration to be finalised.

The administration area was fully decorated and once ironmongery is fitted to the doors, this area will be locked down.

The flooring to the main hall is being installed and all decoration and light installation was completed at the beginning of the week.

The sports hall doors and lights were installed and the changing room ceilings erected.

The music department is awaiting door ironmongery to allow it to be locked down, ready for a de snag.

The maths and English departments are finalised and the corridor is having its final decoration ready for lock down.

The humanities department decoration was completed and is ready for lock down.

The DT department is being decorated and the flooring is being completed.

Respite Centre

Suspended ceiling grid progressing well both floors. IPS frame work / panelling to the wet areas and W/C are progressing well.

Installations of the door linings/ frames ongoing to both floors.

Skirting and architrave ongoing to both floors now.

External render ongoing.

Decoration ongoing to both floors.

Stair balustrade ongoing.

External timber cladding ongoing.

   
Site Phasing Plan: PLC Building Phasing Plan
   
Community Engagement:

 

This week we hosted pupils from Ysgol Maes Dyfan as part of their Experience of Work week

We took them around the new building and they met several of our workers along the way.

  

In addition, we delivered a team building event for over 200 Ysgol Y Deri staff during their Inset Day.

  

 

Project images can be seen by click HERE.