Week Nr: 83
Week Commencing: 5th May 2014
Description of Works:

Ysgol Y Deri

The multi purpose/ main hall decoration and high level lighting plus ventilation is to be completed this week, with the under floor heating and Junkers flooring due to start next week.

The Trampoline and sports hall is being prepared for the installation of the trampoline and flooring by our specialist contractors.

Data cabinets are being installed to electrical cupboards.

Doors and furniture are now 100% complete.

Fixed furniture is now 100% complete with ceramic tiles and plumbing being completed after installation.

Mechanical and electrical installation is now at final fix stage.

Vinyl and lino flooring is now 85% fitted in all the rooms.

Lighting and power is 85% complete to all rooms.

Tiling to the pool area is ongoing with the majority of the works to be complete by next week, and we will soon be filling the pool with water for test and commissioning purposes.

St. Cyres School

The 6th form area is being snagged ready for final inspection and the corridor is being prepared for decoration.

The science department is fully decorated and the tiling to the labs is being finished.

The full height stairs have been decorated on the top floor to allow the scaffolding to be struck.

The administration area had all its doors fitted and is ready for the flooring in the corridors to be installed.

The Headmasters office and the Welsh BACCS rooms were decorated and the main hall is still having its flooring installed.

The maths and English department has been locked down ready for snagging and the corridor is having its final decoration.

The Humanities and languages department is locked down and awaiting the flooring to be installed in the corridor.

The ceiling is to the LRC is currently being installed.

The Music department has had the vinyl flooring to the corridor installed and the drama studio and ICT rooms have been prepared ready for decoration.

The ceilings to the change village were installed and the walls decorated.

The science department is locked down and awaiting the flooring to the corridor and the Art department was decorated.

The SEN area was decorated and prepared for the flooring to be installed.

Respite Centre

Suspended ceiling grid now complete to both floors and tile installation commenced.

IPS frame work / panelling to the wet areas and W/C are nearing completion.

Installations of the door linings/ frames now complete to both floors.

Skirting and architrave now complete to both floors now. Floor coverings commenced – prep work pre smooth works and vinyl being laid to wet rooms and kitchen areas.

External render ongoing.

Decoration ongoing to both floors.

2nd fix electrical works commence – socket covers light fittings etc.

Stair balustrade ongoing.

External timber cladding ongoing.

External Works

Top soiling works to grassed areas and planter commenced ongoing site wide.

Sully road entrance widening works progressing well.

Kerbs and footpath edgings being installed and progressing well site wide.  

Prep works ongoing in readiness for paving and tarmac areas site wide.

Site Phasing Plan: PLC Building Phasing Plan
Community Engagement:

We’ve hosted quite a few staff site tours this week. Everyone’s getting really excited to move into their new school! 

Project images can be seen by click HERE.