Week Nr: 85
   
Week Commencing: 19th May 2014
   
Description of Works:

Ysgol Y Deri

The multi purpose/ main hall, under floor heating and Junkers flooring has been completed.

The Trampoline and sports hall, electrical 1st fix is ongoing as preparation for the installation of the trampoline and flooring by our specialist contractors.

Data cabinets are being installed to electrical cupboards.

Mechanical and electrical installation is now at final fix stage.

Vinyl and lino flooring is now complete in all the rooms.

Main reception floor tiling is available to start on the 27th.

Tiling to the pool area is now complete, with the majority of all specialist contractor works to be complete by next week, and we will soon be filling the pool with water for test and commissioning purposes.

Final fix and commissioning works are well underway.

Shine kitchen and catering fit out is nearing completion in 2 of the 3 areas of works, classrooms and offices are being prepared for handover to be snagged by the Clerk of Works.

St. Cyres School

The 6th form area has been final snagged and the corridor flooring has been installed with all lights being on in this area.

 

The science department labs are having the work benches and sinks completed to allow the area to be snagged. The corridor flooring has also commenced and lights are on.

The Admin area is awaiting de snagging and removal of temporary lights and power.

The Main hall flooring has been completed and the lighting and sound is being finalised.

The fitness suite is awaiting final decoration with all plasterboard works finished this week.

The corridor ceilings are being constructed and the floors are being prepared for the finishes.

The Maths and English department have been snagged and are awaiting inspection before locking down.

The centralised toilets are being decorated and the humanities department is being de snagged.

The music area is waiting inspection and the ICT suites are having their floors prepared.

The sports hall has been redecorated and the externals change has had its final coat of paint.

The CDT department is having its specialist equipment fitted and the corridor walls are being finalised ready for decoration.

 

Respite Centre

 

Ceiling tile installation is ongoing to corridors on both floors.

IPS frame work / panelling to the wet areas and W/C are nearing completion.

Doors and ironmongery installation ongoing to first floor.

Floor coverings ongoing - prep work pre smooth works and vinyl being laid to wet rooms and kitchen areas completed.

Decoration mist coat and 1st coat works ongoing to both floors.

2nd fix electrical works ongoing – socket covers, light fittings etc. 2nd fix on sanitary wear to wet rooms ongoing.

External render awaiting top coat.

Timber cladding ongoing.

 

External Works

 

Top soiling works to grassed areas and planters ongoing site wide.

Brickwork to planters ongoing.

Sully road entrance widening works progressing well.

Kerbs and footpath edgings being installed and progressing well site wide.

Prep works ongoing in readiness for paving and tarmac areas site wide.

Tarmac base course ongoing.

 

   
Site Phasing Plan: PLC Building Phasing Plan
   
Community Engagement:

 

Our penultimate Community Open day was held this week. Our last Community Open Day before the schools break for summer will be held on 18th June: 2pm – 4pm and 5pm – 6pm.

We also hosted head teachers from the St. Cyres feeder primary schools who were taken around the new building. They were very impressed and enthusiastic.

 

Project images can be seen by click HERE.